Contract Agreement Amount

Rs. 3,21,44,708

Physical Progress

98.58%

Financial Progress

97.16%

Remaining Payment

Rs. 2

Road Rehabilitation works on Chaukhutte-Sanfe-Mangalsen Road Section

Office: डिभिजन सडक कार्यालय, साँफेवगर, अछाम (178)

Fiscal Year: 078-79

98.58%

Contract Date: 4-Apr-22

Start Date: 4-Apr-22

Completion Date: 14-Jul-2022 (EOT Not Done)

Project Description

No description available.