Contract Agreement Amount
Rs. 10,88,36,488
Physical Progress
100.00%
Financial Progress
97.13%
Remaining Payment
Rs. 2
Construction Of Pre-Stress RCC Girder Bridge Over Rangunkhola along laldhunga-Katal Road,Dadeldhura
Office: सडक डिभिजन, डोटी (35)
Fiscal Year: 070-71
Contract Date: 13-Jul-14
Start Date: 13-Jul-14
Completion Date: 15-Dec-2019 (EOT Done)
Project Description
No description available.