Contract Agreement Amount

Rs. 10,88,36,488

Physical Progress

100.00%

Financial Progress

97.13%

Remaining Payment

Rs. 2

Construction Of Pre-Stress RCC Girder Bridge Over Rangunkhola along laldhunga-Katal Road,Dadeldhura

Office: सडक डिभिजन, डोटी (35)

Fiscal Year: 070-71

100.00%

Contract Date: 13-Jul-14

Start Date: 13-Jul-14

Completion Date: 15-Dec-2019 (EOT Done)

Project Description

No description available.