Contract Agreement Amount
Rs. 11,96,320
Physical Progress
100.00%
Financial Progress
97.12%
Remaining Payment
Rs. 2
Drainage works with structural steel grates along Siddhartha Highway.
Office: सडक डिभिजन, पाल्पा (27)
Fiscal Year: 077-78
Contract Date: 7-Feb-21
Start Date: 7-Feb-21
Completion Date: 30-May-2021 (EOT Not Done)
Project Description
No description available.