Contract Agreement Amount

Rs. 1,76,48,017

Physical Progress

98.00%

Financial Progress

97.10%

Remaining Payment

Rs. 2

Pavement Work including Cross drainage and retaining Structures along Barmaniya Chowk dekhi Gherabani Chowk samma jane Sadak, Sundar Haraincha, Morang

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 078-79

98.00%

Contract Date: 3-Feb-22

Start Date: 3-Feb-22

Completion Date: 14-Jul-2022 (EOT Done)

Project Description

No description available.