Contract Agreement Amount
Rs. 90,97,465
Physical Progress
100.00%
Financial Progress
97.09%
Remaining Payment
Rs. 2
Road Upgrading Works on ARM (Dhulikhel Section)
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 077-78
Contract Date: 8-Apr-21
Start Date: 8-Apr-21
Completion Date: 09-Jul-2021 (EOT Not Done)
Project Description
No description available.