Contract Agreement Amount
Rs. 1,11,57,467
Physical Progress
0.00%
Financial Progress
97.06%
Remaining Payment
Rs. 2
Road Way Excavation & Structure Works along Bhartola-Uku-Sera Road (From Sera Side).
Office: सडक डिभिजन, बैतडी (36)
Fiscal Year: 076-77
Contract Date: 18-Jun-20
Start Date: 18-Jun-20
Completion Date: 04-Jan-2021 (EOT Done)
Project Description
No description available.