Contract Agreement Amount
Rs. 8,32,15,973
Physical Progress
0.00%
Financial Progress
97.03%
Remaining Payment
Rs. 2
Construction of Pavement (DBSD) and Drains (Side and Cross Drains) along Simara Colvi Road, Bara
Office: डिभिजन सडक कार्यालय, मकवानपुर (19)
Fiscal Year: 073-74
Contract Date: 7-Mar-17
Start Date: 7-Mar-17
Completion Date: 12-Apr-2020 (EOT Done)