Contract Agreement Amount

Rs. 3,20,82,394

Physical Progress

0.00%

Financial Progress

97.02%

Remaining Payment

Rs. 2

Construction of Motorable Prestressed RCC Bridge over Dudhe Khola

Office: डिभिजन सडक कार्यालय, ईलाम (12)

Fiscal Year: 073-74

0.00%

Contract Date: 28-Nov-16

Start Date: 28-Nov-16

Completion Date: 18-Apr-2019 (EOT Done)

Project Description

No description available.