Contract Agreement Amount

Rs. 12,32,356

Physical Progress

99.00%

Financial Progress

0.00%

Remaining Payment

Rs. 100

RE Maintenance of Araniko Highway ch59+000-74+000

Office: सडक डिभिजन, पोखरा (26)

Fiscal Year: 075-76

99.00%

Contract Date: 30-May-19

Start Date: 30-May-19

Completion Date: 01-Jul-2019 (EOT Not Done)

Project Description

No description available.