Contract Agreement Amount
Rs. 1,80,55,414
Physical Progress
0.00%
Financial Progress
96.97%
Remaining Payment
Rs. 3
Roadway excavation,Hume pipe,culvert,Gabion,Masonry wall,Construction of side drain and Gravelling works along DeuraliThati to Dandakateri(Ch.144+000-156+000)
Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)
Fiscal Year: 076-77
Contract Date: 27-Mar-20
Start Date: 27-Mar-20
Completion Date: 18-Sep-2021 (EOT Not Done)