Contract Agreement Amount
Rs. 2,46,77,255
Physical Progress
100.00%
Financial Progress
96.96%
Remaining Payment
Rs. 3
Rehabilitation works of Gurje-Chhahare Section, Samakhusi-Tokha-Gurje-Bidur Road, NH40
Office: डिभिजन सडक कार्यालय, धनकुटा (15)
Fiscal Year: 078-79
Contract Date: 23-Feb-22
Start Date: 23-Feb-22
Completion Date: 10-Apr-2023 (EOT Done)
Project Description