Contract Agreement Amount
Rs. 8,80,50,883
Physical Progress
88.00%
Financial Progress
96.95%
Remaining Payment
Rs. 3
Construction of Pre-stressed RCC Bridge over Setigandaki River at Khairenitar-9, Tanahun.
Office: सडक डिभिजन, तनहुं (25)
Fiscal Year: 071-72
Contract Date: 15-Jul-15
Start Date: 15-Jul-15
Completion Date: 08-Jul-2023 (EOT Done)
Project Description