Contract Agreement Amount
Rs. 26,40,422
Physical Progress
97.46%
Financial Progress
96.95%
Remaining Payment
Rs. 3
Roadway Excavation and Structural Works in Dhamigaaun-Waima-Mankunde-Purchodi-Haat Road
Office: डिभिजन सडक कार्यालय, सिराहा (16)
Fiscal Year: 079-80
Contract Date: 10-Nov-22
Start Date: 10-Nov-22
Completion Date: 14-Mar-2023 (EOT Not Done)
Project Description
No description available.