Contract Agreement Amount

Rs. 12,30,100

Physical Progress

0.00%

Financial Progress

96.94%

Remaining Payment

Rs. 3

"Cross Drainage Works at Dhulikhel-Sindhuli-Bardibas Road".

Office: सूर्यविनायक-धुलिखेल​, धुलिखेल-सिन्धुली-बर्दिवास सडक आयोजना, काठमाण्डौ (225)

Fiscal Year: 076-77

0.00%

Contract Date: 9-Jun-20

Start Date: 9-Jun-20

Completion Date: 09-Jul-2020 (EOT Not Done)

Project Description

No description available.