Contract Agreement Amount
Rs. 2,46,02,526
Physical Progress
0.00%
Financial Progress
96.92%
Remaining Payment
Rs. 3
Construction of Road structures,Cross drainage,Black Top & Earthworks from Gaiko Goth(Chainage 73+300) to Bihar Thati(Chainage 73+800)and from Chainage 75+600 to Chainage 76+300 section along Saljhandi-Sandhikharka-Dhorpatan Road
Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)
Fiscal Year: 076-77
Contract Date: 27-Mar-20
Start Date: 27-Mar-20
Completion Date: 01-Jan-1970 (EOT Not Done)
Project Description
No description available.