Contract Agreement Amount

Rs. 12,97,78,610

Physical Progress

100.00%

Financial Progress

96.91%

Remaining Payment

Rs. 3

Road Safety works from Buddhachowk to Tikabhairab (Ch. 0+000 to 79+000Km)

Office: कान्ती लोकपथ सडक योजना, ललितपुर (87)

Fiscal Year: 064-65

100.00%

Contract Date: 13-Jul-16

Start Date: 13-Jul-16

Completion Date: 03-Jan-2021 (EOT Done)

Project Description

No description available.