Contract Agreement Amount

Rs. 4,69,67,473

Physical Progress

90.09%

Financial Progress

96.89%

Remaining Payment

Rs. 3

Rehabilitation work along MRM (Haraincha mod-Gachiya section)

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 078-79

90.09%

Contract Date: 8-Dec-21

Start Date: 8-Dec-21

Completion Date: 14-Jan-2023 (EOT Done)

Project Description

No description available.