Contract Agreement Amount
Rs. 66,69,982
Physical Progress
25.00%
Financial Progress
96.88%
Remaining Payment
Rs. 3
Construction of 4 M Slab Culverts on Satdobato Bagdada Gaikhur sadak, Gorkha
Office: Unknown (1)
Fiscal Year: 079-80
Contract Date: 25-Jan-23
Start Date: 25-Jan-23
Completion Date: 10-Jul-2023 (EOT Not Done)
Project Description
No description available.