Contract Agreement Amount

Rs. 66,69,982

Physical Progress

25.00%

Financial Progress

96.88%

Remaining Payment

Rs. 3

Construction of 4 M Slab Culverts on Satdobato Bagdada Gaikhur sadak, Gorkha

Office: Unknown (1)

Fiscal Year: 079-80

25.00%

Contract Date: 25-Jan-23

Start Date: 25-Jan-23

Completion Date: 10-Jul-2023 (EOT Not Done)

Project Description

No description available.