Contract Agreement Amount

Rs. 10,12,160

Physical Progress

100.00%

Financial Progress

96.85%

Remaining Payment

Rs. 3

Road upgrading works at Nawadurga Chok Ekta Chowk Hinchok Ukalo Suryabinayak 4

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 077-78

100.00%

Contract Date: 27-Jun-21

Start Date: 27-Jun-21

Completion Date: 16-Oct-2021 (EOT Not Done)

Project Description

No description available.