Contract Agreement Amount
Rs. 44,87,463
Physical Progress
0.00%
Financial Progress
96.84%
Remaining Payment
Rs. 3
Upgrading of Jiri Salleri Dhingri Namche Sadak, Dolakha
Office: डिभिजन सडक कार्यालय, दोलखा (18)
Fiscal Year: 075-76
Contract Date: 22-Apr-19
Start Date: 22-Apr-19
Completion Date: 10-Jul-2019 (EOT Not Done)
Project Description
No description available.