Contract Agreement Amount
Rs. 55,96,70,065
Physical Progress
64.28%
Financial Progress
96.83%
Remaining Payment
Rs. 3
Upgrading and Construction of Rani-Biratnagar-Itahari-Dharan Road to six lane standards (Ch: km 23+200 to 26+400)
Office: व्यापारिक मार्ग विस्तार आयोजना (रानी-बिराटनगर-इटहरी-धरान मार्ग), सुनसरी (154)
Fiscal Year: 072-73
Contract Date: 9-Sep-16
Start Date: 9-Sep-16
Completion Date: 13-Apr-2022 (EOT Done)
Project Description
No description available.