Contract Agreement Amount
Rs. 27,07,295
Physical Progress
100.00%
Financial Progress
96.81%
Remaining Payment
Rs. 3
Road Upgrading Works along Ranjakhola - Banakhu - Ghartichhap - Gokule - Jagathali - Taldhunga - Milchhe Road
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 076-77
Contract Date: 11-Jun-20
Start Date: 11-Jun-20
Completion Date: 05-Nov-2020 (EOT Not Done)
Project Description
No description available.