Contract Agreement Amount
Rs. 13,80,753
Physical Progress
0.00%
Financial Progress
96.80%
Remaining Payment
Rs. 3
Patch Work (Recurrent Maintenance) at Bardibas-Sindhuligadhi Road Section
Office: सूर्यविनायक-धुलिखेल, धुलिखेल-सिन्धुली-बर्दिवास सडक आयोजना, काठमाण्डौ (225)
Fiscal Year: 075-76
Contract Date: 19-Aug-18
Start Date: 19-Aug-18
Completion Date: 17-Nov-2018 (EOT Not Done)
Project Description
No description available.