Contract Agreement Amount
Rs. 44,38,969
Physical Progress
100.00%
Financial Progress
96.76%
Remaining Payment
Rs. 3
Service Track Upgrading and Drain Maintenance Works on Araniko Rajmarga CH 13+100 to CH 19+800 (Suryabinayak - Sanga Section)
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 077-78
Contract Date: 7-Apr-21
Start Date: 7-Apr-21
Completion Date: 09-Jul-2021 (EOT Not Done)