Contract Agreement Amount

Rs. 42,00,583

Physical Progress

100.00%

Financial Progress

96.74%

Remaining Payment

Rs. 3

Road Uppgrading Works on Kamalpokhari Lakila Changhu Sankhu Sadak

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 077-78

100.00%

Contract Date: 26-Apr-21

Start Date: 26-Apr-21

Completion Date: 09-Jul-2021 (EOT Not Done)

Project Description

No description available.