Contract Agreement Amount

Rs. 2,69,96,301

Physical Progress

100.00%

Financial Progress

96.73%

Remaining Payment

Rs. 3

Road Improvement Works on Gaur Pipara Madhopur Binagra Dhobiniya Manpur Sahid Smarak Jaynagar Dipahi Chok Khesrahiya Bhlehi Bhediyahi Rajpur Tulasi Pachrukhi Sabik Matsari-3 Bagmati Baadh Sadak, Rautahat

Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)

Fiscal Year: 078-79

100.00%

Contract Date: 12-Apr-22

Start Date: 12-Apr-22

Completion Date: 30-Mar-2023 (EOT Done)

Project Description

No description available.