Contract Agreement Amount
Rs. 13,25,200
Physical Progress
0.00%
Financial Progress
96.72%
Remaining Payment
Rs. 3
Repair of potholes and Road Edges on Gurje-Chhahare section of Samakhushi Tokha Gurje Bidur Road(NH 40)
Office: डिभिजन सडक कार्यालय, नुवाकोट (21)
Fiscal Year: 076-77
Contract Date: 14-Nov-19
Start Date: 14-Nov-19
Completion Date: 12-Mar-2020 (EOT Not Done)
Project Description
No description available.