Contract Agreement Amount
Rs. 2,34,53,571
Physical Progress
96.72%
Financial Progress
96.72%
Remaining Payment
Rs. 3
Roadway Excavation (Rock Cutting) and Construction of Road Structures from Chainage 292+540 to 292+750 and 306+981 to 307+400 of Mahakali Corridor, Darchula
Office: Unknown (1)
Fiscal Year: 080-81
Contract Date: 17-Dec-23
Start Date: 17-Dec-23
Completion Date: 14-Jul-2024 (EOT Not Done)
Project Description
No description available.