Contract Agreement Amount

Rs. 18,05,632

Physical Progress

100.00%

Financial Progress

96.71%

Remaining Payment

Rs. 3

Road Widening and upgrading works on Mandev club chapakhal rifel dada pauwa Changunarayan 4 And Pipalbot Tajmot jane Bato ma Culvert Retaining Wall,Changunarayan 4

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 077-78

100.00%

Contract Date: 3-Jan-21

Start Date: 3-Jan-21

Completion Date: 18-May-2021 (EOT Not Done)