Contract Agreement Amount

Rs. 3,56,17,442

Physical Progress

8.97%

Financial Progress

96.69%

Remaining Payment

Rs. 3

Road Rehabilitation and Widening Work Along Karnali Highway, (Pili to Galje Section) at ch 175+000 to 189+000, Kalikot (RDJML/33701138/078/79-04)

Office: डिभिजन सडक कार्यालय, जुम्ला (179)

Fiscal Year: 078-79

8.97%

Contract Date: 28-Sep-21

Start Date: 28-Sep-21

Completion Date: 20-Apr-2023 (EOT Done)