Contract Agreement Amount
Rs. 23,74,269
Physical Progress
100.00%
Financial Progress
96.64%
Remaining Payment
Rs. 3
Traffic Safety works at Milti-Manthali-Khurkot Road
Office: डिभिजन सडक कार्यालय, खुर्कोट (185)
Fiscal Year: 078-79
Contract Date: 3-Feb-22
Start Date: 24-Feb-22
Completion Date: 09-Jul-2022 (EOT Not Done)