Contract Agreement Amount

Rs. 1,05,27,315

Physical Progress

96.63%

Financial Progress

96.63%

Remaining Payment

Rs. 3

Gravelling work, Masonary Drain and Structure, Cross drainage work on Na.Na Pa. 1-9 Jadne sadak, Dailekh

Office: सडक डिभिजन, सुर्खेत (33)

Fiscal Year: 076-77

96.63%

Contract Date: 18-Jun-20

Start Date: 18-Jun-20

Completion Date: 12-Feb-2021 (EOT Not Done)

Project Description

No description available.