Contract Agreement Amount

Rs. 2,07,55,000

Physical Progress

97.00%

Financial Progress

96.58%

Remaining Payment

Rs. 3

Roadway Excavation work on Naigad- Sisne Road Section of Koilabas- Chunubang- Rukumkot- Sisne-Dolpa Road

Office: डिभिजन सडक कार्यालय, चौरजहारी (181)

Fiscal Year: 076-77

97.00%

Contract Date: 14-Jul-20

Start Date: 22-Jul-20

Completion Date: 12-Apr-2021 (EOT Not Done)

Project Description

No description available.