Contract Agreement Amount
Rs. 2,07,55,000
Physical Progress
97.00%
Financial Progress
96.58%
Remaining Payment
Rs. 3
Roadway Excavation work on Naigad- Sisne Road Section of Koilabas- Chunubang- Rukumkot- Sisne-Dolpa Road
Office: डिभिजन सडक कार्यालय, चौरजहारी (181)
Fiscal Year: 076-77
Contract Date: 14-Jul-20
Start Date: 22-Jul-20
Completion Date: 12-Apr-2021 (EOT Not Done)
Project Description
No description available.