Contract Agreement Amount

Rs. 42,61,465

Physical Progress

100.00%

Financial Progress

96.53%

Remaining Payment

Rs. 3

Road widening&upgrading works at Saraswatikhel buspark somthali suyalgaun khadkadil sadak cha na pa 1

Office: सडक डिभिजन, भक्तपुर (24)

Fiscal Year: 077-78

100.00%

Contract Date: 28-Apr-21

Start Date: 28-Apr-21

Completion Date: 09-Jul-2021 (EOT Not Done)

Project Description

No description available.