Contract Agreement Amount
Rs. 1,46,46,350
Physical Progress
0.00%
Financial Progress
96.45%
Remaining Payment
Rs. 3
Flexible Pavement Works at Kamala-Sindhuli Section of Dhulikhel-Sindhuli Bardibas Road
Office: सूर्यविनायक-धुलिखेल, धुलिखेल-सिन्धुली-बर्दिवास सडक आयोजना, काठमाण्डौ (225)
Fiscal Year: 077-78
Contract Date: 25-Apr-21
Start Date: 25-Apr-21
Completion Date: 10-Jul-2021 (EOT Not Done)
Project Description
No description available.