Contract Agreement Amount

Rs. 46,14,50,832

Physical Progress

92.00%

Financial Progress

96.43%

Remaining Payment

Rs. 3

Extention & Improvement of Mohanapul Attariya Road

Office: मोहनापुल अत्तरीया सडक योजना कार्यालय, कैलाली (220)

Fiscal Year: 073-74

92.00%

Contract Date: 15-May-17

Start Date: 15-May-17

Completion Date: 13-Apr-2022 (EOT Done)

Project Description

No description available.