Contract Agreement Amount
Rs. 21,82,374
Physical Progress
0.00%
Financial Progress
96.42%
Remaining Payment
Rs. 3
Road Upgrading Works on Mulpani Gaudol Nagarkot Road,Changunarayan 4, Bhaktapur
Office: सडक डिभिजन, भक्तपुर (24)
Fiscal Year: 076-77
Contract Date: 3-Dec-19
Start Date: 3-Dec-19
Completion Date: 08-Mar-2020 (EOT Not Done)
Project Description
No description available.