Contract Agreement Amount
Rs. 9,19,840
Physical Progress
0.00%
Financial Progress
96.35%
Remaining Payment
Rs. 3
Humepipe Culvert Works on Dumre Besisahar Road & Prithivi Lokmarga
Office: सडक डिभिजन, तनहुं (25)
Fiscal Year: 073-74
Contract Date: 28-May-17
Start Date: 28-May-17
Completion Date: 06-Jul-2017 (EOT Not Done)
Project Description
No description available.