Contract Agreement Amount
Rs. 10,20,000
Physical Progress
0.00%
Financial Progress
96.34%
Remaining Payment
Rs. 3
M/s Shaksham Nirman Sewa ,Lalitpur
Office: डिभिजन सडक कार्यालय, ललितपुर (23)
Fiscal Year: 076-77
Contract Date: 4-Oct-19
Start Date: 4-Oct-19
Completion Date: 29-Jan-2020 (EOT Not Done)
Project Description
No description available.