Contract Agreement Amount
Rs. 9,58,06,474
Physical Progress
55.00%
Financial Progress
96.29%
Remaining Payment
Rs. 3
Construction of Blacktop Road(DBST), Humepipe, Slab, Box Culvert on Pasamari Balubari Road, Jhapa
Office: डिभिजन सडक कार्यालय, झापा (13)
Fiscal Year: 073-74
Contract Date: 6-Feb-17
Start Date: 6-Feb-17
Completion Date: 21-Mar-2020 (EOT Done)
Project Description
No description available.