Contract Agreement Amount

Rs. 9,58,06,474

Physical Progress

55.00%

Financial Progress

96.29%

Remaining Payment

Rs. 3

Construction of Blacktop Road(DBST), Humepipe, Slab, Box Culvert on Pasamari Balubari Road, Jhapa

Office: डिभिजन सडक कार्यालय, झापा (13)

Fiscal Year: 073-74

55.00%

Contract Date: 6-Feb-17

Start Date: 6-Feb-17

Completion Date: 21-Mar-2020 (EOT Done)

Project Description

No description available.