Contract Agreement Amount
Rs. 18,40,26,454
Physical Progress
95.00%
Financial Progress
96.28%
Remaining Payment
Rs. 3
Construction of Road structures,pavement works DBSD and traffic safety works from chainage 58+000 balebang to ch.70+000,Sandhikharka
Office: सालझण्डी सन्धिखर्क ढोरपाटन सडक योजना, अर्घाखांची (92)
Fiscal Year: 075-76
Contract Date: 8-Dec-19
Start Date: 23-Dec-19
Completion Date: 09-Aug-2022 (EOT Not Done)