Contract Agreement Amount

Rs. 5,42,90,003

Physical Progress

97.13%

Financial Progress

96.24%

Remaining Payment

Rs. 3

Shyam sundar-Saud jv

Office: धनगढी-खुटिया-दिपायल-चैनपुर-उरैभन्ज्याङ्ग सडक योजना, बि.पी‍. नगर, डाेटी (294)

Fiscal Year: 073-74

97.13%

Contract Date: 9-Jul-17

Start Date: 25-Jul-17

Completion Date: 12-Jun-2024 (EOT Done)

Project Description

No description available.