Contract Agreement Amount
Rs. 14,88,96,939
Physical Progress
96.00%
Financial Progress
96.23%
Remaining Payment
Rs. 3
Himsagarmatha Construction Pvt. Ltd.,Bharatpur,Chitwan
Office: मध्यमाञ्चल क्षेत्रिय सडक निर्देशनालय, काठमाण्डौ (8)
Fiscal Year: 079-80
Contract Date: 7-Jul-23
Start Date: 7-Jul-23
Completion Date: 28-May-2024 (EOT Done)