Contract Agreement Amount
Rs. 8,07,80,936
Physical Progress
100.00%
Financial Progress
96.21%
Remaining Payment
Rs. 3
Construction of Four Lane Road along Chandranigahpur Gaur Road, Rautahat
Office: हेभिईक्युपमेन्ट डिभिजन, मकवानपुर (38)
Fiscal Year: 079-80
Contract Date: 13-Jun-23
Start Date: 13-Jun-23
Completion Date: 12-May-2024 (EOT Not Done)
Project Description
No description available.