Contract Agreement Amount
Rs. 1,71,30,903
Physical Progress
100.00%
Financial Progress
96.20%
Remaining Payment
Rs. 3
Construction of Vented Causeway, Approach Road, River Training Works along Lalbakaiya River Bridge at Garja, Rautahat
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 074-75
Contract Date: 23-Apr-18
Start Date: 23-Apr-18
Completion Date: 16-Mar-2019 (EOT Not Done)
Project Description
No description available.