Contract Agreement Amount
Rs. 8,35,45,777
Physical Progress
96.00%
Financial Progress
96.18%
Remaining Payment
Rs. 3
Lohandra Khola Bridge Construction work Duhabi Tetariya Motipur Chandragadhi Sadak Motipur, Morang
Office: डिभिजन सडक कार्यालय, मोरङ (14)
Fiscal Year: 074-75
Contract Date: 26-Apr-18
Start Date: 3-May-18
Completion Date: 14-Jan-2023 (EOT Done)
Project Description
No description available.