Contract Agreement Amount

Rs. 8,35,45,777

Physical Progress

96.00%

Financial Progress

96.18%

Remaining Payment

Rs. 3

Lohandra Khola Bridge Construction work Duhabi Tetariya Motipur Chandragadhi Sadak Motipur, Morang

Office: डिभिजन सडक कार्यालय, मोरङ (14)

Fiscal Year: 074-75

96.00%

Contract Date: 26-Apr-18

Start Date: 3-May-18

Completion Date: 14-Jan-2023 (EOT Done)

Project Description

No description available.