Contract Agreement Amount

Rs. 6,80,51,493

Physical Progress

100.00%

Financial Progress

96.18%

Remaining Payment

Rs. 3

Construction RCC Bridge over Balma River, Daiji Beldandi Road, Kanchanpur

Office: सडक डिभिजन, कञ्चनपुर (34)

Fiscal Year: 071-72

100.00%

Contract Date: 10-Jan-16

Start Date: 10-Jan-16

Completion Date: 30-Jul-2021 (EOT Done)

Project Description

No description available.