Contract Agreement Amount
Rs. 61,79,528
Physical Progress
0.00%
Financial Progress
96.12%
Remaining Payment
Rs. 3
Malangwa-5 dekhi Lakhandehi Nadi Kamalamaisthan Bishnu Ga.Pa.-6 Simara Gau Sadak, Sarlahi
Office: डिभिजन सडक कार्यालय, चन्द्रनिगाहापुर, गौर (176)
Fiscal Year: 076-77
Contract Date: 11-Dec-19
Start Date: 11-Dec-19
Completion Date: 29-Jun-2020 (EOT Not Done)
Project Description
No description available.