Contract Agreement Amount

Rs. 79,04,470

Physical Progress

100.00%

Financial Progress

96.12%

Remaining Payment

Rs. 3

Recurrent Maintenance Works at MRM Butwal- Kothi Section and SRM Chidiyakhola-Siddhababa Section

Office: यान्त्रिक कार्यालय, सुर्खेत (50)

Fiscal Year: 078-79

100.00%

Contract Date: 16-Aug-22

Start Date: 16-Aug-22

Completion Date: 17-Dec-2022 (EOT Not Done)

Project Description

No description available.