Contract Agreement Amount

Rs. 1,89,73,756

Physical Progress

0.00%

Financial Progress

96.10%

Remaining Payment

Rs. 3

Construction of RCC Motorable Bridge over Chaurjahari Banskhola(Varyal /Pangrayan) khola on Devesthal Chaurjahari Road

Office: डिभिजन सडक कार्यालय, चौरजहारी (181)

Fiscal Year: 072-73

0.00%

Contract Date: 14-Jul-16

Start Date: 14-Jul-16

Completion Date: 13-Mar-2020 (EOT Done)

Project Description

No description available.