Contract Agreement Amount
Rs. 1,89,73,756
Physical Progress
0.00%
Financial Progress
96.10%
Remaining Payment
Rs. 3
Construction of RCC Motorable Bridge over Chaurjahari Banskhola(Varyal /Pangrayan) khola on Devesthal Chaurjahari Road
Office: डिभिजन सडक कार्यालय, चौरजहारी (181)
Fiscal Year: 072-73
Contract Date: 14-Jul-16
Start Date: 14-Jul-16
Completion Date: 13-Mar-2020 (EOT Done)
Project Description
No description available.